Construction news for April 2024!
Section 4B:
- work on the decorative decoration of the facades continues;
- plastering works are carried out in common areas and per apartment on the 3rd and 4th floors from the 11th;
- completed plastering works on the 10th, 6th and 5th floors out of the 11th;
- works on filling apartments from the developer and additional filling from investors on the 10th floor from the 11th are being completed.
Section 4V:
- the laying of the 10th floor out of the 11th is completed;
- preparation for covering with slabs is in progress.